 Following article describes cost for construction of residential building in USA. As a thumb rule cost per square feet of construction area is calculated for budget preparation. The construction cost can be divided under several head, the most common cost heads are
Following article describes cost for construction of residential building in USA. As a thumb rule cost per square feet of construction area is calculated for budget preparation. The construction cost can be divided under several head, the most common cost heads are
- Consultant cost -this includes cost involved for architectural design, structural design, services design etc. The cost varies between Rs 43 -45 per Sft and about 2.5 % of total construction cost.
- Civil works – The highest cost involved in this construction phase which includes excavation, footings, RCC work, Block work, plaster etc. The cost varies between Rs. 980 – 1000/- per Sft and about 53% of total project cost.
- Finishing works – This include all finishes work i.e flooring, painting, marble works, wood works, MS railing, Gypsum plaster etc.The cost varies between Rs 420 – 450 /- per Sft. and about 23 % of total construction cost.
- Services works – this includes essential services like plumbing, electrical , HVAC , fire fighting etc. The cost of CP, sanitary and other fitting are also included in this. the cost varies between Rs 305 – 320 /- per Sft and about 17% of total construction cost.
- Site establishment and temporary works – this includes cost for barricading, clearing site, water and electrical charges for construction activities, site office construction etc. The cost varies between Rs 85 -90 /- per Sft. and about 4.5 % of total construction cost.
The table below gives more details idea about construction cost for each activities.
| Sr. No. | Contract Code and Name | Cost per Sqfoot | % of total cost | 
| A. Consultants | |||
| 1 | Architectural desigining | 21.85173 | 1.2 | 
| 2 | Structural desigining | 7.283911 | 0.4 | 
| 3 | Services | 13.11104 | 0.7 | 
| 7 | Model making | 1.098774 | 0.1 | 
| 9 | Plot Survey | 0.137347 | 0.0 | 
| Total | 43.83311 | 2.4 | |
| B. Civil Works | |||
| 1 | Excavation | 15.96403 | 0.9 | 
| 2 | Antitermite treatment | 0.106861 | 0.0 | 
| 3 | Sub structure Waterproofing, | 3.965101 | 0.2 | 
| 4 | RCC works, Blockwork, Plaster, Misc civil works | 966.7697 | 52.0 | 
| Total | 986.8057 | 53.1 | |
| C. Finishing Works | |||
| 1 | FLOORING | 142.01 | 7.6 | 
| 2 | Kitchen Platform with Sink | 21.41376 | 1.2 | 
| 3 | Entrance lobby & signage | 9.15645 | 0.5 | 
| 4 | Wood works | 67.81992 | 3.6 | 
| 5 | Waterproofing | 12.74205 | 0.7 | 
| 6 | Gypsum Plaster | 36.52273 | 2.0 | 
| 7 | P.O.P false ceiling | 6.498941 | 0.3 | 
| 8 | External Painting | 20.82378 | 1.1 | 
| 9 | Internal Painting | 21.26266 | 1.1 | 
| 10 | staircase painting | 1.912218 | 0.1 | 
| 11 | Lift Shaft Painting | 0.345885 | 0.0 | 
| 12 | Duct Painting | 2.53158 | 0.1 | 
| 13 | Ceiling paint | 7.623122 | 0.4 | 
| 14 | Aluminum Window | 46.1979 | 2.5 | 
| 17 | M.S Railing | 11.16349 | 0.6 | 
| 18 | Façade work | 6.190976 | 0.3 | 
| Total | 419.6929 | 22.6 | |
| D. Services | |||
| 1 | Plumbing& pumping | 51.57279 | 2.8 | 
| 2 | CP Sanitary (Jaquar & Roca) | 44.45325 | 2.4 | 
| 3 | Firefighting | 23.43493 | 1.3 | 
| 4 | Electrical | 76.44474 | 4.1 | 
| 5 | Lifts | 82.40805 | 4.4 | 
| 6 | IBMS | 16.33613 | 0.9 | 
| 7 | Solar water system | 4.395096 | 0.2 | 
| 8 | DG Set | 6.592644 | 0.4 | 
| Total | 305.6376 | 16.4 | |
| Initial Total (A+B+C+D) | 1755.969 | 94.4 | |
| Site eastablishment | 33.01863 | 1.8 | |
| Electrical & water charges 1.5% | 26.33954 | 1.4 | |
| Contingenices for temp. works | 17.55969 | 0.9 | |
| EHS budget | 8.779847 | 0.5 | |
| Construction Cost / Sft | 1859.227 | 100.0 | 